  1. news from weibo said last contact is with Ho Chi Minh traffic control... FB said some fly passenger already contact with family
  2. Update Image from BinaPuri Website date 20 August 2013
  3. hard to open partially, due to main terminal Section 2 (S2) still not complete, it include all system Departure, arrival, also custom and immigration.
  4. Also as a backup control tower..MAHB mention before.
  5. Airasia and other airline hanger, maybe include cargo
  6. update from binaPuri website, date is around 23 May.
  7. issue delay more in design change after AA requirement (bigger capacity and runway.).BHS/Aerobridges just part of issue..also Malindo join at 2012.
  8. Increase in building size is to handle more passenger traffic up to 45 million, but base on MAHB forecast, KLIA2 will reach 45m passenger traffic in 2028+-. event Airasia forecast KLIA 2 can reach 45m passenger traffic in 2020. seriously event i thinking KLIA2 is a bit small ...... Don't think taxiway is un-piled, maybe we can see the construction photo weather is piled or not.
  9. If follow the klia2 project, final revised design only fix on 4th quarter 2010 after add new requirement from Airasia... 1st design is in 2009. construction just 2 year++ from 2011 to now reach 90% progress is quite good for an airport project, just MAHB over optimist on opening date.
  10. new progress image from BinaPuri website,
  11. new picture form binapuri website, picture should be taken on last week of March
  12. only have 31/1 from UEM builder look ceiling very low
×
×